- Set up profile boards and string lines correctly for a building outline
- Apply the 3-4-5 method to verify corners are exactly 90 degrees
- Transfer levels using a water level (hose pipe)
- Excavate trenches to the correct depth and width from the drawing
- Place blinding concrete, strip footing concrete, and build substructure walling to DPC level
- Identify site safety requirements including trench safety and PPE
Kuhusu
Learn to set out building lines, use profile boards and string lines, check square with the 3-4-5 method, and construct strip foundations to DPC level.
Kilichomo ndani· masomo 11
- 1About This Pack
- 2Reading the Site Plan
- 3Setting Up Profile Boards
- 4The 3-4-5 Method
- 5On Site: Profile Boards and String Lines
- 6Transferring Levels with a Water Level
- 7Excavating Trenches Safely
- 8Blinding and Strip Footing Concrete
- 9Substructure Walling, DPC and Hardcore
- 10Site Terms